Converting a Viennese Altbau: Which Permits and Consents You Need, and in What Order

By Richard DobrohruschkaUpdated 2026-11-05

Survey plan of a Viennese Altbau flat with marked walls and notes
In short: For a conversion in a Viennese Altbau (the pre-1945 apartment building), depending on the intervention you need the consent of the property management (Hausverwaltung) or the co-owners, of the landlord in a rented flat, and where load-bearing elements, shafts or the façade are affected, usually also the involvement of the building authority (Baupolizei, MA 37). Renewing surfaces is generally unproblematic; walls, pipework and façade often are not. Which steps exactly are needed is best clarified case by case with the property management, the building authority and a structural engineer. Asked in the right order, these questions take less effort than most people fear.

At the owners' meeting you mention your plan in passing, and suddenly words like consent, structural engineering and protected zone fill the room. Imagine a couple who have bought an owner-occupied flat in a Gründerzeit building (late nineteenth-century Viennese apartment block) on the Spittelberg. High ceilings, box-type windows, a dark kitchen at the end of the corridor. Their wish sounds simple: the wall between kitchen and living room should go, the bathroom should be larger, and in summer an air-conditioning unit would be nice. On the way home they wonder whether they have taken on too much. They have not. They only need the right sequence, and with it they can already picture what comes next: a bright open kitchen, a generous bathroom, a flat that stays cool in July. This article sorts out who has a say in a conversion in a Viennese Altbau and how to prepare permits calmly.

An important note in advance: this article gives general orientation from planning practice. It is no substitute for legal advice or for information from the authority. Every building and every intervention is different.

Contents
  1. Who has a say in an Altbau conversion
  2. Owner-occupied flats: the consent of the co-owners
  3. The building authority: when MA 37 comes into play
  4. Structural engineering: why the engineer often comes first
  5. Listed buildings, protected zones and the façade
  6. Typical projects and who has a say
  7. How to proceed: six steps
  8. Frequently asked questions
  9. What happens next

Who has a say in an Altbau conversion

In a conversion of a Viennese Altbau flat, several bodies can be involved. Not all are relevant to every project, but it helps to know them:

  • Property management (Hausverwaltung): It knows the building, administers the shared parts and knows which rules apply in the house. It is usually the first port of call.
  • Co-owners: In an owner-occupied flat they have a say when shared parts of the building or their own interests are affected.
  • Landlord: In a rented flat, significant changes generally require his or her consent.
  • Building authority (Baupolizei, MA 37): The City of Vienna's building authority is responsible when an intervention is relevant under building law, for instance with load-bearing elements.
  • Structural engineer: He or she assesses whether and how an intervention in the load-bearing structure is possible, and provides the basis for many further steps.
  • Other bodies: For listed buildings, in protected zones, with gas appliances or flue systems, additional bodies or specialists such as the chimney sweep may have to be involved.

For the couple on the Spittelberg, almost all of these bodies ended up involved, though not for every wish. The wall concerned structural engineering, co-owners and the building authority. The bathroom concerned mainly the property management because of the riser. The air-conditioning unit concerned the façade. Let us look at them one by one, starting with the co-owners.

Anyone who owns a flat may decide a great deal inside it. Limits arise where common parts of the building are touched or where the interests of other owners may be affected. These typically include load-bearing walls and ceilings, shared pipes and risers, shafts, chimneys and the façade.

In such cases the consent of the other owners generally has to be obtained. How this works in the specific building is something the property management knows. Sometimes a written consent is enough, sometimes the matter is dealt with at the owners' meeting. What matters is that the documents are easy to understand: a plan, a short description and, where necessary, a statement from the structural engineer.

Our experience is that co-owners rarely refuse on principle. They want to know whether their flat is affected, whether it will be loud and for how long. Anyone who informs openly makes consent easier.

Rented flats: the landlord has a say

In a rented flat the room for manoeuvre is narrower. For significant changes, for example to walls, pipework or plumbing installations, the landlord's consent is generally required. Also clarify what happens to the changes when you move out. A written agreement creates clarity for both sides. Then the authority has its own say.

Most consents fail not because of the substance but because of an unclear request.

The building authority: when MA 37 comes into play

Vienna's building code distinguishes, put simply, between projects that are possible without involving the authority, projects that must be notified to it, and projects that need a building permit. Which category applies depends on the specific intervention, and that is exactly what should be clarified before work begins.

As a rough guide: renewing surfaces, floors, tiles and sanitaryware in the same place is generally unproblematic under building law. Interventions in load-bearing elements, changes to the façade or to shafts, and changes in the use of individual rooms, on the other hand, may require the involvement of the building authority (MA 37). Whether a submission plan is needed and which documents go with it, we clarify case by case with the authority, the structural engineer and, where necessary, a civil engineer (Ziviltechniker).

For clients this above all means: build these steps into the schedule. Official procedures have their own deadlines, which cannot be shortened at will. How this fits into a realistic sequence is shown in the article on the timeline of a flat renovation. But why does the structural engineer so often come first?

Structural engineering: why the engineer often comes first

In a Viennese Altbau it is not always obvious at first glance which wall is load-bearing. Spine walls almost always carry load, but even seemingly light partitions can take loads, for instance because ceilings have settled over the decades. That is why any intervention in walls or ceilings begins with an assessment by a structural engineer.

The engineer checks the situation on site, assesses the load-bearing structure and, where possible, proposes a solution, such as a steel beam over a new opening. His or her statement is often the basis for the co-owners' consent and for the documents sent to the authority. What is possible when opening a load-bearing wall and what it means is explained in the article Removing a load-bearing wall in Vienna. How the open kitchen then succeeds is described in the article on the open-plan kitchen-living space.

With the couple on the Spittelberg, it turned out that the wall to the kitchen really did carry load. The solution was not a complete opening but a wide passage with a beam and a sliding glass door. The result feels more open than expected and was approvable with considerably less effort.

Imagine standing in the new wide passage. The beam is tucked into the edge of the ceiling, the sliding glass door is open, and the light from the kitchen window reaches the far wall of the living room.

A further advantage of an early structural assessment: it stops wishes becoming too specific before it is clear whether they are feasible. Anyone who learns only after the concept presentation that the planned opening is not possible loses time and often enthusiasm. That is why, for us, the structural engineer belongs in the site-survey phase, not in the detailed planning.

Skipping the clarifications has a price that rarely announces itself. A wish pursued without asking sends you back to the drawing board when the wall turns out to be load-bearing. A missing consent can stop a building site that has already begun. An unclear request is answered with a no. The weeks saved at the start are lost in the middle. And what about the outside of the building, with its own rules?

Listed buildings, protected zones and the façade

Many Viennese Gründerzeit buildings lie in protected zones, and some are listed. This affects above all the outward appearance: façade, windows, roof and visible building elements. Interiors are usually less affected in buildings in protected zones, whereas in listed buildings there can also be requirements inside, for example for stucco, doors or historic floors.

For clients this means: everything that has an effect on the outside needs particular care. An air-conditioning unit on the façade, new windows or an altered terrace may require additional consents. Whether a building is listed or lies in a protected zone can be clarified in advance, and the property management usually knows.

For the couple on the Spittelberg, the air-conditioning unit on the façade became a different solution: a unit with its outdoor part in the inner courtyard, agreed with the property management and the co-owners. What alternatives there are for pleasant temperatures is shown in the article Heating and cooling via surfaces.

Imagine a July afternoon in the finished flat. The air is cool, the façade looks as it always did from the street, and the only sound is the faint hum of the unit in the courtyard, out of sight.

Typical projects and who has a say

The following overview is a guide from practice, not a legal classification. In an individual case it may differ.

ProjectProperty management, owners or landlordBuilding authority (MA 37)Structural engineer
Renewing floors, tiles, paintingusually just observe the house rulesgenerally not needednot needed
Renewing a bathroom in the same placeinform if work affects the risergenerally not needednot needed
Relocating bathroom or WCconsent usually neededcheck depending on the interventionwhere the ceiling is affected
Moving a non-load-bearing wallinform, depending on the buildingcheck depending on the interventioncheck that it really is non-load-bearing
Opening a load-bearing wallconsent generally neededinvolvement generally neededessential
Air-conditioning unit, windows, façadeconsent generally neededcheck depending on location and protected zoneusually not needed
Changing a gas boiler or flue systeminformcheck depending on the interventionnot needed, but plumber and chimney sweep

If you want to join two flats, further questions arise, for example on the land register situation and the owners' association. The article Combining two flats describes the planning side. And in what order do you proceed?

How to proceed: six steps

An orderly approach saves time and nerves. This sequence has proved its worth on our projects:

  1. Collect and prioritise wishes. What should change? Which interventions are really necessary, which would be nice?
  2. Check the existing structure. Survey, inspection of walls and pipework, assessment of which elements are affected.
  3. Bring in the structural engineer. For any intervention in walls or ceilings, before planning what is not possible.
  4. Inform the property management early. Clarify which consents are needed and how they are obtained in the building.
  5. Prepare the documents. Plans, description, structural engineer's statement and, if needed, submission documents for the building authority.
  6. Bring the neighbours along. A short notice or a personal conversation about duration and noisy phases often works wonders.

At Richard Atelier this preparation is part of the planning. We talk to the property management, the structural engineer and, where necessary, the authority, and prepare documents so that they are easy to understand. How this coordination is embedded in the project sequence is described in the articles Working with an interior designer and Planning and execution from a single source. The Team page shows who stands behind the planning. The Tischlerkultur joinery behind our planning has been family-run since 1935. The first conversation is free, lasts 30 minutes and takes place by phone or video, so you can find out where you stand before you spend anything.

Anyone who wins the property management over as an ally has already covered half the distance.

Frequently asked questions

Do I need a permit to renovate a bathroom in an Altbau?

If the bathroom is renewed in the same place and only surfaces and sanitaryware are replaced, this is generally possible without involving the authority. For work on shared pipes such as the riser, the property management should be involved. If the bathroom is relocated or the ceiling is affected, further clarification is needed. You will find more on execution on the bathroom renovation page. Before you plan, we tell you which case applies to you.

May I remove a wall in my owner-occupied flat?

With non-load-bearing walls this is often possible, but should still be confirmed by a structural engineer, because in an Altbau even light walls can carry loads. With load-bearing walls a structural solution, the co-owners' consent and the involvement of the building authority (MA 37) are generally required. We clarify this case by case before any planning, and the first step is always to look at the wall.

What does MA 37 do in a flat conversion?

MA 37 is the City of Vienna's building authority. It is responsible when a conversion is relevant under building law, for example with interventions in load-bearing elements or certain changes to the façade and shafts. Whether and in what form it must be involved depends on the specific project. You do not have to work this out alone.

How long does it take for consents to be in place?

That varies greatly. A written consent from the property management may be in place within a few weeks, whereas dealing with the matter at the owners' meeting or an official procedure often takes longer. That is why these steps should begin in parallel with planning, and we build realistic waiting times into your schedule.

What happens if I convert without the necessary consent?

Without the necessary consent you risk disputes with co-owners or landlord, orders from the authority and, in the worst case, having to reverse the work. There can also be problems on a later sale. It pays to clarify properly beforehand what is required, and we help you find out before work begins.

Do I have to inform my neighbours about the conversion?

There is no legal duty to inform personally in every case, but it is wise and fair. A short notice stating the duration, noisy phases and a contact person prevents many conflicts. The house rules often additionally regulate at what times noisy work is allowed. A friendly notice in the stairwell is often all it takes.

What happens next

Back to the walk home from the owners' meeting and the feeling of having taken on too much. Soon it could be a clear list of who must agree, in what order, with the documents already prepared. If you are planning a conversion in an Altbau and are unsure which consents you will need, call us or book the initial conversation: 30 minutes by phone or video, free, without obligation. We listen to your project and tell you which questions to clarify first.

Afterwards we record the key points in a project sheet, and one person accompanies you through the clarifications with the property management, the structural engineer and the authority.

Read next: Removing a load-bearing wall in Vienna, Renovating an Altbau flat in Vienna, The bathroom in a Viennese Altbau, The realistic timeline of a renovation

How do you want to live? Tell us.

Leave your e-mail and phone number, it takes less than a minute. Richard gets back to you personally, usually within one working day. Free, no obligation, no sales pitch.

I am interested in

By sending you agree that we process your details to get in touch. See our privacy policy.

+43 660 3607188WhatsApp

Prefer to pick a time slot right away?Book online (German booking page)

Related articles

Process, Costs & Planning

Renovating a Flat: The Realistic Timeline from First Idea to Moving In

How long does a flat renovation take in Vienna? A realistic timeline with every phase, lead times and permits, so you know the day you will move in.

9 min read
Process, Costs & Planning

What Does a Bathroom Renovation Cost in Vienna? Items, Cost Drivers and Savings Traps

What does a bathroom renovation cost in Vienna? Cost drivers, every item from demolition to taps, the Altbau factor and the false economies to avoid.

9 min read
Process, Costs & Planning

What Does a Complete Interior Concept Cost? An Honest Answer, Without Guesswork

What does interior design cost in Vienna? See what the fee and the construction budget of a complete concept depend on, and where saving really pays off.

9 min read
Room Transitions

Removing a Load-Bearing Wall in Vienna: What Is Possible, What It Costs, Who Decides

Removing a load-bearing wall in Vienna: who has a say, what drives the cost, and how engineer, authority and process open your Altbau into one bright room.

9 min read
Process, Costs & Planning

Working with an Interior Designer: How the Process Unfolds and What Is Asked of You

Working with an interior designer in Vienna: from first consultation through concept and planning to handover, and what your own role is in each phase.

11 min read
Process, Costs & Planning

What Does a Fitted Kitchen Cost in Vienna? What the Price Really Depends On

What does a fitted kitchen cost in Vienna? What the price depends on, the main cost blocks from fronts to appliances, and where you can save wisely.

9 min read

Back to the journal

Call Book a free consultation